South Huron is committed to providing the best recreational opportunities that are accessible, benefit all age groups and abilities, and are affordable for the entire community.
The following recreation renewal projects are planned to begin in 2022:
- South Huron Recreation Centre Renewal Project
- Stephen Township Arena Renewal Project
This page will be kept current with progress as these projects move forward.

South Huron Recreation Centre (SHRC) Renewal Project (Phase 1)
Project Status: Construction
IMPORTANT INFORMATION: Reopening of the South Huron Recreation Centre on Monday September 19, 2022 |
After nearly 4 months of construction, we are excited to welcome you back to the South Huron Recreation Centre (SHRC) on Monday September 19th for ice usage.
What you need to know before you visit the South Huron Recreation Centre:
Facility Component
|
Important Information for Users
|
Navigating the facility
|
It is important to note that although the SHRC will reopen on September 19th, there may be construction activities ongoing within the facility as contractors work on outstanding items and the next components of the project. Please follow posted signage at the facility to ensure the safety of both patrons and workers.
|
Temporary Entrance
|
Patrons are to use the east entrance only to enter and exit the facility. Signage will be posted at the facility to direct patrons to the east side of the building. The west entrance is temporarily closed and usage is not permitted at any time.
|
Parking
|
Parking is available on the east and north side of the facility, with limited parking on the west due to the temporary construction area. There is currently one designated accessible parking space at the east side of the facility, adjacent to the temporary entrance. Outside of daytime Monday to Friday, overflow parking may be available along Victoria Street East.
|
Ice Usage
|
Ice usage resumed on Monday September 19, 2022
|
Trophy Display and Information Boards
|
We will be working with all groups over the next few months to identify a coordinated plan moving forward for the display of trophies and information boards in the facility. Stay tuned!
|
Hall Rentals
|
It is anticipated that the hall and kitchen will reopen for rentals to the public on November 1, 2022.
|
Construction of Zone 2 (new dressing room addition)
|
Work related to the construction of the new dressing room addition will continue into the fall of 2022. The temporary construction area on the west side of the SHRC will remain in place until project completion. There will be no impact to ice users inside the facility during this period.
|
|
Project Background |
At the Regular Council meeting on June 7, 2021, Council approved a renovation and retrofit of the South Huron Recreation Centre (SHRC) that will help promote and sustain multi-generational programs and services at the facility (See the news release June 9, 2021: Council Greenlights SHRC Project)
|
Project Scope |
The Municipality has undertaken a review of the facility and is proposing a renovation and retrofit that will include two phases.
The first phase, scheduled for construction in 2022, will enhance ice user experiences, increase comfort and optimal viewing for patrons, while improving the overall accessibility within the main areas of the facility.
The first phase (as approved) includes the following general parameters:
- Dressing room addition consisting of 6 new dressing rooms, 1 officials’ room, 1 mechanical and electrical room and a connecting corridor. Note: the existing dressing rooms will be repurposed in their current footprint based on future consultation and the existing officials' room will remain unchanged to accommodate request for use.
- New dasher board and netting system
- Expansion of existing warm room to open concept lobby
- Front entrance improvements
- Incorporation of existing offices and entrances
- Addition of two universal washrooms and viewing platform that meet AODA standards
- Site development
The total allocated construction budget for the above components is $4,500,000 plus HST.
Council approved the following additional items:
|
Proposed Milestones and Project Status |
Milestone | Timing | Status |
RFP: Design and Contract Administration |
January 2022 |
Completed
Invizij Architects were awarded the Design and Contract Administration at the Regular Council meeting on January 17, 2022 (See the RFP award report: January 17, 2022)
|
Design Development |
February/March 2022 |
Completed
Invizij Architects presented the Design Schematic at the March 7, 2022 Regular Council Meeting. Council motioned to accept the Design Schematic, as presented (See the staff report re: SHRC Design Approval March 7, 2022)
|
Tender Preparation, Release and Award for Construction |
April 2022 |
Tender awarded at the Regular Council meeting on June 6, 2022. |
Facility Closed to Public Access |
June 2022 - August 2022 |
Completed |
Construction Period |
June to October 2022 (Anticipated)
|
- Completed: Zone 1 (interior work)
- In progress: Zone 2 (addition)
|
Ice Usage Resumes |
September 19, 2022 |
Completed |
Hall Rentals Resume |
November 1, 2022 |
Completed |
|

Stephen Township Arena Renewal Project
Project Status: Completed
Project Background |
At the Regular Council meeting on February 16, 2021, Council passed motion #039-2021 "That the Stephen Arena remain open and continue to operate as an arena". This work is necessary to continue operations at the Stephen Arena. This project will diversify the facility to meet future program demand.
To support Council's motion:
|
Project Scope |
It was identified that significant work is needed to continue operations at the arena, while diversifying the facility to meet future program demands.
The capital upgrades scheduled for construction in 2022 were included in the approved budget and includes the following general parameters:
- Rink slab replacement and components (existing sand floor to concrete)
- Replacement of dasher boards and glass
- Front entrance improvements to meet AODA standards
The total amount approved by Council for the Stephen Township Arena Renewal project for the above components is $2,000,000.
Council approved the following additional items:
|
Proposed Milestones and Project Status |
Milestone | Timing | Status |
Project Initiation |
February/March 2022 |
Completed
|
Design Development |
February/March 2022 |
Completed
|
Facility Closed to Public Access (as per regular ice removal schedule) |
Evening of April 3, 2022 |
Completed |
Tender Preparation, Release and Award for Construction |
March/April 2022 |
Ice Rink Floor - Tender awarded at the Regular Council meeting on Tuesday April 19, 2022
Dasherboard System - Tender awarded at the Regular Council meeting on Monday May 16, 2022
|
Construction Period |
May 2022 - August 2022 (Anticipated) |
Completed - Ice Rink Floor
Completed - Dasherboard System
Completed - Accessible Front Doors
|
Ice Usage Resumes |
October 17, 2022
|
Completed
|
New Bleacher Installation |
January 2023
|
Completed |
|