Victoria St E Reconstruction Project-Weekly Update July 4, 2025
The Contractor has completed the installation of concrete curbs between Main Street and the pillars. Installation of the sanitary sewer continued east of the pillars.
Next week the Contractor will install sidewalks between Main Street and the pillars. The temporary watermain east of the pillars will be commissioned and placed in service. Sanitary sewer installation will continue, and storm sewer work will commence east of the pillars.
Victoria Street is closed to through traffic from Main Street to the east end of Victoria Street. Access to the Relouw Early Childhood Learning Centre will be maintained through the South Huron Recreation Centre property. Access to the Exeter Public School and recreation facilities at the east end of Victoria Street has limited access.
Your patience and understanding is greatly appreciated
Contact Us
The Municipality of South Huron
322 Main Street South, P.O. Box 759
Exeter, ON N0M 1S6
Phone: 519-235-0310
Sign up to receive municipal news to your email inbox