Victoria St E Reconstruction Project-Weekly Update August 1, 2025
The Contractor has completed the installation of the new watermain east of the pillars to Pryde Blvd. The gravel road base has been completed east of the pillars to the end of Victoria Street. Work on the new South Huron Recreation Centre entrance continues.
Next week the Contractor will start commissioning the new watermain east of the pillars to Pryde Boulevard. Work on the new South Huron Recreation Centre entrance and parking lot will continue.
Victoria Street is closed to through traffic from Main Street to the east end of Victoria Street. Access to the Relouw Early Childhood Learning Centre will be maintained through the South Huron Recreation Centre property. Access to the Exeter Public School and recreation facilities at the east end of Victoria Street is limited. Your patience and understanding is greatly appreciated.
Contact Us
The Municipality of South Huron
322 Main Street South, P.O. Box 759
Exeter, ON N0M 1S6
Phone: 519-235-0310
Sign up to receive municipal news to your email inbox