Victoria St E Reconstruction Project-Weekly Update August 8, 2025
The Contractor has completed the road excavation and granular road base east of the pillars. Testing and commissioning the new watermain east of the pillars to Pryde Boulevard is underway. Work on the new South Huron Recreation Centre entrance is complete to the granular road base.
Next week, after successful commissioning of the new watermain east of the pillars, the contractor will make the final connections and decommission the temporary watermain. Installation of curbs and sidewalks east of the pillars is scheduled for next week and base asphalt is scheduled for the week of August 25th.
Victoria Street is closed to through traffic from Main Street to the east end of Victoria Street. Access to the Relouw Early Childhood Learning Centre will be maintained through the South Huron Recreation Centre property. Access to the Exeter Public School and recreation facilities at the east end of Victoria Street is limited. Your patience and understanding is greatly appreciated.
Contact Us
The Municipality of South Huron
322 Main Street South, P.O. Box 759
Exeter, ON N0M 1S6
Phone: 519-235-0310
Sign up to receive municipal news to your email inbox