Victoria St E Reconstruction Project-Weekly Update August 22, 2025

The Contractor has completed all storm sewers, sanitary sewers, watermains, gravel road base, curbs, and sidewalks. Boulevard topsoil work continues in preparation for hydroseeding.

 Next week the contractor is scheduled to place the base asphalt on Victoria Street, pave asphalt driveway aprons, and install the new pedestrian crosswalk hardware near the school. The contractor plans to demobilize next week and have all equipment moved off site by the end of the week.

Victoria Street is closed to through traffic from Main Street to the east end of Victoria Street. Access to the Relouw Early Childhood Learning Centre will be maintained through the South Huron Recreation Centre property. Access to the Exeter Public School and recreation facilities at the east end of Victoria Street is limited. Your patience and understanding is greatly appreciated.

Contact Us

The Municipality of South Huron
322 Main Street South, P.O. Box 759
Exeter, ON N0M 1S6
Phone: 519-235-0310

Sign up to receive municipal news to your email inbox

 

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.