Main Street South Reconstruction Project-Weekly Update June 12, 2026
This week the contractor continued the installation of sanitary services and main line storm sewer. Next week the contractor will complete the installation of the main line storm sewer and continue the installation of catchbasins, storm services and sanitary services. Road work will continue with excavation to subgrade and placing granular road base as required to maintain access. Northbound traffic (one lane) will remain on Main Street; and southbound traffic will continue to be detoured onto Church and William Street until construction is complete on the west side of Main Street.
Businesses remain open during construction; access to homes and businesses will be reasonably maintained throughout construction. With traffic disrupted and detours in place, please expect delays and plan accordingly.
Your patience and understanding is greatly appreciated.