Main Street South Reconstruction Project-Weekly Update September 4, 2026
This week the contractor continued work on the east side of Main Street, between Wellington Street and Hill Street, with removals, watermain installation, and installation of services. Next week the contractor will continue work on the east side of Main Street. One lane of traffic in both directions will remain on Main Street until completion of all work on the east side of the roadway.
Businesses remain open during construction; access to homes and businesses will be reasonably maintained throughout construction. With traffic disrupted and lanes reduced, please expect delays and plan accordingly. Your patience and understanding is greatly appreciated.