The construction project will be constructed in three phases in 2026, with the final layer of surface asphalt being placed in 2027.
The first phase of the construction project is scheduled to begin after the Easter weekend; and is expected to take one week to complete.
· The first phase will be the replacement of sanitary sewers, storm sewers, and watermains in the intersection of Main Street and Church Street. This will require a full road closure to complete the work. The intersection will be re-paved before reopening the roadway.
The second phase of the construction project is scheduled to begin immediately after completion of phase 1 and is expected to be completed by September 2026.
· The second phase of the project is the reconstruction of the west side of Main Street (Ausable River bridge to Victoria Street), with replacement/installation of a sanitary sewer, storm sewer, and installation of new curb, sidewalk, and base asphalt. Southbound traffic will be detoured to William Street and northbound traffic will be shifted to the east side of Main Street during this phase (one lane only).
The third phase of the construction project is scheduled to begin immediately after completion of phase 2 and is expected to be completed prior to the end of 2026.
· The third phase of the project is the reconstruction of the east side of Main Street (Ausable River bridge to Victoria Street), with replacement of the watermain, and installation of new curb, sidewalk, and base asphalt. Northbound traffic will be detoured to Andrew Street and southbound traffic will be shifted to the west side of Main Street during this phase (one lane only).
Like all construction projects, delays are expected during peak construction periods. The project team is committed to providing ongoing communication about the project to alleviate the impact of construction as much as possible.
To alleviate the volume of truck traffic during construction, a truck detour will be set up on Kirkton Road, Morrison Line and Thames Road to divert heavy trucks around the construction area.