The construction project will be constructed in two phases in 2027, with the final layer of surface asphalt being placed in 2028.
The first phase of the construction project is scheduled to begin in the spring of 2027; and is expected to be completed by September 2027.
- The first phase of the project is the reconstruction of the west side of Main Street (Victoria Street to Sanders Street), with replacement/installation of a sanitary sewer, storm sewer, and installation of new curb, sidewalk, and base asphalt. Southbound traffic will be detoured to William Street and northbound traffic will be shifted to the east side of Main Street during this phase (one lane only).
The second phase of the construction project is scheduled to begin immediately after completion of phase 2 and is expected to be completed prior to the end of 2027.
- The second phase of the project is the reconstruction of the east side of Main Street (Victoria Street to Sanders Street), with replacement of the watermain, and installation of new curb, sidewalk, and base asphalt. Northbound traffic will be detoured to Andrew Street and southbound traffic will be shifted to the west side of Main Street during this phase (one lane only).
Like all construction projects, delays are expected during peak construction periods. The project team is committed to providing ongoing communication about the project to alleviate the impact of construction as much as possible.
To alleviate the volume of truck traffic during construction, a truck detour will be set up on Kirkton Road, Morrison Line and Thames Road to divert heavy trucks around the construction area.